Project information
Location:
Germany
Customer product:
Double Wall Plant, Power Plus
Project description
Performance RT: Planning, Support for design of shuttering robot
Plant capacity: 320 m² double wall/shift oder 750 m² double wall/shift
Hall: Area 3.290 m², Clearance 8,35 m
Personnel: 10 employees/shift (wall); 8 employees/shift (slab)
Plant concept:
- Double Wall 180 – 400 mm
- Double Wall and lattice girder slab with curved overlapping reinforcement
- 40 pallets L/W 12,5/3,3 m
- Tilting bypass station
- Shuttering robot, also for magnet box and magnets for inserts.
- Automated straightening and cutting machine fo round steel
- Possibility to produce core insulated double walls
- Direct concrete transport from a new mixing plant
- Divided hall
- Inside the hall a large stacking and interim storage area for precast elements
- Plant with high potential
Project description
For this third plant our customer demanded a high-duty plant including a shuttering robot to reduce personnel costs. Together with the plant a main pc was installed. Also a data connection/transfer between all 3 factories is realized.
Conclusion:
A flexible and high potential plant with a possibility to extend product range.